Question 71

Report
Export
Collapse

The product owner determines how many product backlog items the developers select for the sprint in the sprint planning.

False, the scrum master does that
False, the scrum master does that
True
True
True, in line with what was promised to the stakeholders
True, in line with what was promised to the stakeholders
True, if the developers have enough capacity
True, if the developers have enough capacity
False, the project manager does that
False, the project manager does that
False
False
Suggested answer: F

Explanation:

It is false, the developers select the items, because they will have to commit to it.

asked 23/09/2024
Priti Agrawal
33 questions

Question 72

Report
Export
Collapse

Several scrum teams share the scrum master. Developers of multiple teams approach the scrum master, because they need fulltime commitment from the same technical specialist for the next sprint. What should the scrum master consider for the response to this problem? Choose the two best answers.

The need for a stable velocity
The need for a stable velocity
The benefit of the teams figuring it out theirselves
The benefit of the teams figuring it out theirselves
The need to have all developers busy with work
The need to have all developers busy with work
The ability of the scrum teams to produce integrated increments
The ability of the scrum teams to produce integrated increments
Suggested answer: B, D

Explanation:

The working increment is the goal of the sprint and should be kept in mind. The self-managing aspect of the teams is also crucial to take in mind. Stable velocity and optimally used developers are not the scrum master's concern.

asked 23/09/2024
Kishi Peart
36 questions

Question 73

Report
Export
Collapse

What is the definition of done good for? Choose all that apply.

This way documentation is obligated and cannot be skipped
This way documentation is obligated and cannot be skipped
It creates a shared understanding of what done means
It creates a shared understanding of what done means
Management knows what the work of the developer needs to be checked for
Management knows what the work of the developer needs to be checked for
It helps the developers know how much work to select during the sprint planning
It helps the developers know how much work to select during the sprint planning
Suggested answer: B, D

Explanation:

The DoD helps the developers know how much work needs to be done, and therefore they can decide what should be part of the sprint. It also creates a shared understanding of what done means. This is likely to include documentation, but that depends on the decisions of the organization and team. Scrum does not dictate this.

asked 23/09/2024
Katherine Messick
37 questions

Question 74

Report
Export
Collapse

How much time will there be after a sprint before the next one starts?

Enough to deploy the increment and update the product backlog based on the outcome of the sprint review
Enough to deploy the increment and update the product backlog based on the outcome of the sprint review
Enough to clean up lingering definition of done points
Enough to clean up lingering definition of done points
None, a new sprint starts immediately after the end of the previous one
None, a new sprint starts immediately after the end of the previous one
At most a week for a one-month sprint
At most a week for a one-month sprint
Suggested answer: C

Explanation:

The scrum guide says: 'A new Sprint starts immediately after the conclusion of the previous Sprint.'

asked 23/09/2024
Jessica Martinada
30 questions

Question 75

Report
Export
Collapse

What do scrum artifacts represent?

Work that needs to be done
Work that needs to be done
Flow and feedback
Flow and feedback
Work or value
Work or value
Visual representation of the progress
Visual representation of the progress
Suggested answer: C

Explanation:

The scrum artifacts are: product backlog, sprint backlog and the increment. They represent work or value.

asked 23/09/2024
Steve Nihan
39 questions

Question 76

Report
Export
Collapse

Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.

True
True
False
False
Suggested answer: A

Explanation:

The scrum guide says: 'The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint.'

asked 23/09/2024
marius trif
47 questions

Question 77

Report
Export
Collapse

What are two responsibilities of testers in the scrum team? (choose two)

Finding bugs
Finding bugs
Tracking quality metrics
Tracking quality metrics
All developers are responsible for quality
All developers are responsible for quality
Verifying the work of the programmers
Verifying the work of the programmers
Scrum has no tester role
Scrum has no tester role
Suggested answer: C, E

Explanation:

Specific roles don't exist in scrum, developers are creating the value.

asked 23/09/2024
Toan Tran
38 questions

Question 78

Report
Export
Collapse

Which three describe TDD?

An incremental and emergent approach to software design
An incremental and emergent approach to software design
A software development technique based on automated tests
A software development technique based on automated tests
A predictable way to develop working well-organized code
A predictable way to develop working well-organized code
Creating a manual test script before writing code
Creating a manual test script before writing code
Having testers involved in the development process
Having testers involved in the development process
Suggested answer: A, B, C

Explanation:

TDD stands for test driven development. It makes developers think before starting to code. This leads to better organized code. It requires the developer to write the code for the test first, this means that it's based on automated tests. There are no testers in scrum, they are called developers as well.

asked 23/09/2024
Thiago B
43 questions

Question 79

Report
Export
Collapse

When does the development team show their work to the product owner?

All of these
All of these
Anytime the developers need feedback from the product owner
Anytime the developers need feedback from the product owner
Whenever the product owner asks
Whenever the product owner asks
During the sprint review
During the sprint review
Suggested answer: A

Explanation:

All of these would good moments to update the PO with the work done.

asked 23/09/2024
ALLIE SEBRONE MUHAMUBI
42 questions

Question 80

Report
Export
Collapse

Which are three attributes of a bad bug report?

Vague statements or untested assumptions
Vague statements or untested assumptions
Assigning blame
Assigning blame
Generic titles
Generic titles
Simple and repeatable reproduction steps
Simple and repeatable reproduction steps
One bug per report
One bug per report
Suggested answer: A, B, C

Explanation:

you don't want to blame anyone, have vague titles of make vague statements. It needs to be clear and constructive, and focussed on one specific problem. It should als not contain feature requests.

asked 23/09/2024