ExamGecko
Home / Scrum / PSM I / Practice Test 1
Ask Question

Scrum PSM I Practice Test 1

Add to Whishlist
00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Yes, but only for Scrum Teams whose work has dependencies.
Yes, but only for Scrum Teams whose work has dependencies.
Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
No, each Scrum Team stands alone.
No, each Scrum Team stands alone.
No, that is far too hard and must be done in a hardening Sprint.
No, that is far too hard and must be done in a hardening Sprint.
Comment (0)
Suggested answer: B
asked 23/09/2024
Mikalai Yurouski
36 questions