SIMULATION

You are a functional consultant for Contoso Entertainment System USA (USMF).

You need to configure the system to ensure that planned master orders generated by Material Requirements Planning (MRP) contain trade agreements.

To complete this task, sign in to Dynamics 365 portal.

A.

Explanation

Answers
A.

Explanation

Suggested answer: A

Explanation:

1. Navigate to the Master Planning Parameters form (Master Planning > Setup > Master Planning Parameters).

2. Select the Planned Orders tab.

3. Select the Find Trade Agreements option.

4. Save the changes.

Reference: https://docs.microsoft.com/en-us/learn/modules/configure-use-master-planning-dyn365-supply-chain-mgmt/03-parameters