All employees at a company work eight hours each day Monday through Friday. A resource named Resource1 has 40 hours available for a specific week.

You need to schedule Resource1 to work on a project during that week. The resource must work the hours detailed below:

Which allocation method should you use?

A.

Remaining capacity

Answers
A.

Remaining capacity

B.

Percentage capacity

Answers
B.

Percentage capacity

C.

Full capacity

Answers
C.

Full capacity

D.

Front-load hours

Answers
D.

Front-load hours

Suggested answer: D

Explanation:

You would have to create separate bookings for each of the working days.

Reference: https://docs.microsoft.com/en-us/dynamics365/project-operations/psa/faq-allocation-methods