Demand and Supply Planning (SAP IBP) implementation has been identified as a quick win, based on feedback from a large cross section of Wanderlust stakeholders. As the Chief Enterprise Architect, you have now been asked to scope and contextualize the architecture project. Architecture principles have already been adopted. Which of the following activities should you to initiate to conclude the Statement of Architecture Work for the intended SAP IBP implementation initiative? Note: There are 3 correct answers to this question.

A.

Conduct a Fit Gap Assessment to identify requirements that cannot be met

Answers
A.

Conduct a Fit Gap Assessment to identify requirements that cannot be met

B.

Define the Solution Context for the architecture work.

Answers
B.

Define the Solution Context for the architecture work.

C.

Conduct a high-level Capability Assessment to identify areas of improvement (business and IT).

Answers
C.

Conduct a high-level Capability Assessment to identify areas of improvement (business and IT).

D.

Conduct a technical Proof of Concept to understand features and functionalities of SAP IBP.

Answers
D.

Conduct a technical Proof of Concept to understand features and functionalities of SAP IBP.

E.

Outline the aspirational Solution Concept to address the stakeholders' needs and business requirements.

Answers
E.

Outline the aspirational Solution Concept to address the stakeholders' needs and business requirements.

Suggested answer: A, B, E

Explanation:

The Statement of Architecture Work should encompass a Fit Gap Assessment to understand what requirements are currently not met by existing capabilities, the definition of the Solution Context to set the boundaries and scope of the architecture project, and the outline of the aspirational Solution Concept that encapsulates the stakeholders' needs and business requirements. These steps are vital in the preparatory phase to ensure that the architecture work is well-defined and targeted to deliver the anticipated outcomes. Reference = These activities are part of standard enterprise architecture practices and are necessary to develop a comprehensive and actionable Statement of Architecture Work that guides the SAP IBP implementation initiative.