Question 14 - CPIM-Part-2 discussion

Report
Export

The sales and operations planning (S&OP) process in an assemble-to-order (ATO) production environment focuses on control of:

A.
end product backlog.
Answers
A.
end product backlog.
B.
finished goods inventory.
Answers
B.
finished goods inventory.
C.
key intermediate part inventory.
Answers
C.
key intermediate part inventory.
D.
raw material inventory.
Answers
D.
raw material inventory.
Suggested answer: C

Explanation:

The S&OP process in an ATO production environment focuses on control of key intermediate part inventory, which are the components or subassemblies that are produced in advance and assembled to order when the customer order is received. By controlling the key intermediate part inventory, the S&OP process can balance the demand and supply of the final products, while reducing the lead time and inventory costs. The key intermediate part inventory is also known as the decoupling point, where the production process switches from MTS to MTO mode. The S&OP process can determine the optimal level of key intermediate part inventory based on the forecast and backlog of customer orders, as well as the production capacity and costs.

The other options are less relevant for the S&OP process in an ATO production environment. End product backlog refers to the customer orders that have not been fulfilled yet. Finished goods inventory refers to the final products that are ready for sale. Raw material inventory refers to the basic materials that are used to produce the components or subassemblies. These types of inventory are more applicable for MTS or MTO production environments, where the production process is either entirely based on forecast or entirely based on sales order. In an ATO production environment, the S&OP process does not need to control these types of inventory, as they are either minimal or nonexistent.Reference: CPIM Part 2 Exam Content Manual, Domain 4: Plan and Manage Supply, Section B: Production Planning and Control, Subsection 1: Production Strategies and Techniques, Page 19;Demand management process in assemble to order (ATO) environment;Assemble-to-Order (ATO): Overview, Examples, Pros and Cons.