Question 9 - CBDA discussion

Report
Export

The research question prompting the use of analytics is well-defined. The team obtains the results and determines that the source data did not provide reliable results. As a result of this finding, the team modifies the original question to one that can be answered by the data. What is a risk that could impact the value of this analysis?

A.
The objective of the original research may not be met
Answers
A.
The objective of the original research may not be met
B.
Timelines will be pushed out making stakeholders unhappy
Answers
B.
Timelines will be pushed out making stakeholders unhappy
C.
Increased costs associated with the source data
Answers
C.
Increased costs associated with the source data
D.
The quality of the analysis may be negatively impacted
Answers
D.
The quality of the analysis may be negatively impacted
Suggested answer: A

Explanation:

The risk that could impact the value of this analysis is that the objective of the original research may not be met, because the team modified the research question to fit the data, rather than finding the data that fits the research question. This could lead to a loss of alignment between the research question and the business problem, stakeholder needs, or analytical methods. The team may end up answering a different or less relevant question than the one they intended to answer, and thus provide less valuable insights or recommendations.

Reference:

* Business Analysis Certification in Data Analytics, CBDA | IIBA, CBDA Competencies, Domain 1: Identify the Research Questions

* Understanding the Guide to Business Data Analytics, page 10-11

* CERTIFICATION IN BUSINESS DATA ANALYTICS HANDBOOK - IIBA, page 8, CBDA Exam Sample Questions and Self-Assessment, Question 10