The outcome from an analytics initiative has resulted in key stakeholders wanting to move forward with a project to redesign the company's website. The business analyst has called a meeting to work on drafting a plan to assess the level of effort required to complete this work. Many of the invited participants redesigned the website before and were invited so they could provide estimates using their knowledge and experience from the past. The business analyst is using which method to estimate this work?

A.
Rolling wave
Answers
A.
Rolling wave
B.
PERT
Answers
B.
PERT
C.
Parametric
Answers
C.
Parametric
D.
Rough order of magnitude
Answers
D.
Rough order of magnitude
Suggested answer: D

Explanation:

The business analyst is using the rough order of magnitude method to estimate this work. This method is based on expert opinion or experience from past projects, and it provides a quick and approximate estimate of the cost, time, or effort required for a project or a task. This method is useful when there is limited information or data available, or when a high-level estimate is needed for planning or budgeting purposes. However, this method also has a high degree of uncertainty and variability, and it should be refined as more details become available12

Reference: 1: Project Estimation Techniques Business Analysts Should Know About 2: Estimation techniques for business analysts -- The Functional BA

asked 18/09/2024
Sze Yenn Tan
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first