ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 158 - CTFL4 discussion

Report
Export

Which of the following BEST defines risk level?

A.
Risk level is determined by calculating the absolute value of the sum of all potential issues that may occur on the project
Answers
A.
Risk level is determined by calculating the absolute value of the sum of all potential issues that may occur on the project
B.
Risk level is calculated by adding the probabilities of all planned risks to a project
Answers
B.
Risk level is calculated by adding the probabilities of all planned risks to a project
C.
Risk level is calculated by dividing the sum of all known risks by the sum of all unknown risks
Answers
C.
Risk level is calculated by dividing the sum of all known risks by the sum of all unknown risks
D.
Risk level is determined by the likelihood of an event happening and the impact or harm from that event
Answers
D.
Risk level is determined by the likelihood of an event happening and the impact or harm from that event
Suggested answer: D

Explanation:

Risk level is determined by the combination of two factors: the likelihood of an event occurring and the impact or harm that could result from that event. This approach allows risks to be prioritized based on their potential effect on the project or system. The likelihood represents the probability of the risk event occurring, while the impact represents the severity of the consequences if the event does happen. This concept is fundamental in risk-based testing and helps guide decision-making during the testing process.

Reference:

ISTQB Certified Tester Foundation Level Syllabus v4.0, Section 1.4.1.

asked 18/09/2024
Elham Alasmari
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first