Which of the following is MOST likely to be an example of a PROJECT risk?

A.
A computation is not always performed correctly in some situations
Answers
A.
A computation is not always performed correctly in some situations
B.
A system architecture may not support some non-functional requirements
Answers
B.
A system architecture may not support some non-functional requirements
C.
Team members' skills may not be sufficient for the assigned work
Answers
C.
Team members' skills may not be sufficient for the assigned work
D.
Specific modules do not adequately meet their intended functions according to the user
Answers
D.
Specific modules do not adequately meet their intended functions according to the user
Suggested answer: C

Explanation:

A project risk relates to potential issues that could affect the overall success of the project. Among the options provided, the risk that 'Team members' skills may not be sufficient for the assigned work' is clearly a project risk because it pertains to the potential failure of the project due to inadequate skillsets among the team. This risk affects the entire project's ability to meet its objectives.

Reference:

ISTQB Certified Tester Foundation Level Syllabus v4.0, Section 1.4.2.