List of questions
Related questions
Question 42 - ITILFND-V4 discussion
Which describes a standard change?
A.
A high-risk change that needs very thorough assessment
B.
A change that is typically implemented as a service request
C.
A change that must be implemented as soon as possible
D.
A change that needs to be scheduled, assessed and authorized following a defined process
Your answer:
0 comments
Sorted by
Leave a comment first