Question 51 - ITILFND-V4 discussion

Report
Export

What are the three phases of 'problem management'?

A.
Problem identification, problem control, error control
Answers
A.
Problem identification, problem control, error control
B.
Problem analysis, error identification, incident resolution
Answers
B.
Problem analysis, error identification, incident resolution
C.
Problem logging, problem classification, problem resolution
Answers
C.
Problem logging, problem classification, problem resolution
D.
Incident management, problem management, change control
Answers
D.
Incident management, problem management, change control
Suggested answer: A