What is the PRIMARY use of a change schedule?

A.
To support the 'incident management' practice and improvement planning
Answers
A.
To support the 'incident management' practice and improvement planning
B.
To manage emergency changes
Answers
B.
To manage emergency changes
C.
To plan changes and help avoid conflicts
Answers
C.
To plan changes and help avoid conflicts
D.
To manage standard changes
Answers
D.
To manage standard changes
Suggested answer: C