Question 214 - ITILFND-V4 discussion
What is a change schedule PRIMARILY used for?
A.
To help plan, authorize and schedule emergency changes
B.
To publish a list of service requests that users can select
C.
To ensure that a single change authority reviews every change
D.
To help plan changes, assist in communication and avoid conflicts