When should a workaround be created?

A.
As soon as possible, once the incident is logged
Answers
A.
As soon as possible, once the incident is logged
B.
After the resolution of a problem
Answers
B.
After the resolution of a problem
C.
When a problem cannot be resolved quickly
Answers
C.
When a problem cannot be resolved quickly
D.
When a potential permanent solution has been identified
Answers
D.
When a potential permanent solution has been identified
Suggested answer: C

Explanation:

Reference: https://www.globalknowledge.com/us-en/resources/resource-library/articles/incidentsand-problems-workarounds/