To which process is work performance information an input?

A.
Administer Procurements
Answers
A.
Administer Procurements
B.
Direct and Manage Project Execution
Answers
B.
Direct and Manage Project Execution
C.
Create WBS
Answers
C.
Create WBS
D.
Perform Qualitative Risk Analysis
Answers
D.
Perform Qualitative Risk Analysis
Suggested answer: A