Which document defines how a project is executed, monitored and controlled, and closed?

A.
Strategic plan
Answers
A.
Strategic plan
B.
Project charter
Answers
B.
Project charter
C.
Project management plan
Answers
C.
Project management plan
D.
Service level agreement
Answers
D.
Service level agreement
Suggested answer: C