Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

A.
Reserve analysis
Answers
A.
Reserve analysis
B.
Three-point estimating
Answers
B.
Three-point estimating
C.
Parametric estimating
Answers
C.
Parametric estimating
D.
Analogous estimating
Answers
D.
Analogous estimating
Suggested answer: D