Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.
Scope baseline
Answers
A.
Scope baseline
B.
Scope management plan
Answers
B.
Scope management plan
C.
Change management plan
Answers
C.
Change management plan
D.
Cost baseline
Answers
D.
Cost baseline
Suggested answer: A