The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

A.
Plan Schedule Management.
Answers
A.
Plan Schedule Management.
B.
Develop Project Charter.
Answers
B.
Develop Project Charter.
C.
Develop Schedule.
Answers
C.
Develop Schedule.
D.
Plan Scope Management.
Answers
D.
Plan Scope Management.