Which tools or techniques are used in the Plan Schedule Management process?

A.
Benchmarking, expert judgment, and analytical techniques
Answers
A.
Benchmarking, expert judgment, and analytical techniques
B.
Statistical sampling, benchmarking, and meetings
Answers
B.
Statistical sampling, benchmarking, and meetings
C.
Negotiations, pre-assignment, and multi-criteria decision analysis
Answers
C.
Negotiations, pre-assignment, and multi-criteria decision analysis
D.
Expert judgment, analytical techniques, and meetings
Most voted
Answers (1)
Most voted
D.
Expert judgment, analytical techniques, and meetings
Suggested answer: D
asked 23/09/2024
Nagaretnam, Ravin
38 questions
User
Your answer:
1 comments
Sorted by
Up
0
Down
User
Cao Trung Kiên

Edited one month ago

Voted D

Expert judgment, analytical techniques, and meetings