A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

A.
Projectized
Answers
A.
Projectized
B.
Weak matrix
Answers
B.
Weak matrix
C.
Functional
Answers
C.
Functional
D.
Balanced matrix
Answers
D.
Balanced matrix
Suggested answer: A