At which point of the project is the uncertainty the highest and the risk of failing the greatest?

A.
Final phase of the project
Answers
A.
Final phase of the project
B.
Start of the project
Answers
B.
Start of the project
C.
End of the project
Answers
C.
End of the project
D.
Midpoint of the project
Answers
D.
Midpoint of the project
Suggested answer: B