Plan Risk Management is the process of defining how to:

A.
Communicate identified risks to the project stakeholders.
Answers
A.
Communicate identified risks to the project stakeholders.
B.
Conduct risk management activities for a project.
Answers
B.
Conduct risk management activities for a project.
C.
Analyze the impact a specific risk may have on the project.
Answers
C.
Analyze the impact a specific risk may have on the project.
D.
Address unexpected risks that may occur during a project.
Answers
D.
Address unexpected risks that may occur during a project.
Suggested answer: B