When does Monitor and Control Risks occur?

A.
At project initiation
Answers
A.
At project initiation
B.
During work performance analysis
Answers
B.
During work performance analysis
C.
Throughout the life of the project
Answers
C.
Throughout the life of the project
D.
At project milestones
Answers
D.
At project milestones
Suggested answer: C