What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A.
Pareto
Answers
A.
Pareto
B.
Ishikawa
Answers
B.
Ishikawa
C.
Shewhart-Deming
Answers
C.
Shewhart-Deming
D.
Delphi
Answers
D.
Delphi
Suggested answer: C