List of questions
Related questions
Question 449 - CAPM discussion
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
A.
BAC
B.
EAC
C.
ETC
D.
WBS
Your answer:
0 comments
Sorted by
Leave a comment first