What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.
Organizational breakdown structure (OBS)
Answers
A.
Organizational breakdown structure (OBS)
B.
Work performance information
Answers
B.
Work performance information
C.
Work package
Answers
C.
Work package
D.
Work breakdown structure (WBS)
Answers
D.
Work breakdown structure (WBS)
Suggested answer: D