The project scope statement and resource calendars are inputs to which Project Time Management process?

A.
Sequence Activities
Answers
A.
Sequence Activities
B.
Estimate Activity Resources
Answers
B.
Estimate Activity Resources
C.
Develop Schedule
Answers
C.
Develop Schedule
D.
Control Schedule
Answers
D.
Control Schedule
Suggested answer: C