Which of the following is an input to the Direct and Manage Project Execution process?

A.
Approved change requests
Answers
A.
Approved change requests
B.
Approved contract documentation
Answers
B.
Approved contract documentation
C.
Work performance information
Answers
C.
Work performance information
D.
Rejected change requests
Answers
D.
Rejected change requests
Suggested answer: A