Question 465 - CAPM discussion
In which process might a project manager use risk reassessment as a tool and technique?
A.
Perform Qualitative Risk Analysis
B.
Monitor and Control Risk
C.
Monitor and Control Project Work
D.
Plan Risk Responses
Your answer: