Which process involves identifying and documenting the logical relationships between project activities?

A.
Develop Schedule
Answers
A.
Develop Schedule
B.
Sequence Activities
Answers
B.
Sequence Activities
C.
Create WBS
Answers
C.
Create WBS
D.
Applying leads and lags
Answers
D.
Applying leads and lags
Suggested answer: B