The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.
Control Schedule.
Answers
A.
Control Schedule.
B.
Quality Control.
Answers
B.
Quality Control.
C.
Perform Integrated Change Control.
Answers
C.
Perform Integrated Change Control.
D.
Develop Schedule.
Answers
D.
Develop Schedule.
Suggested answer: A