When should an iteration backlog be created?

A.
When planning the Kanban board or other put method.
Answers
A.
When planning the Kanban board or other put method.
B.
At the beginning of each project.
Answers
B.
At the beginning of each project.
C.
When defining the MBI (Minimum Business Increment).
Answers
C.
When defining the MBI (Minimum Business Increment).
D.
At the beginning of each sprint.
Answers
D.
At the beginning of each sprint.
Suggested answer: D

Explanation:

An iteration backlog (or sprint backlog) is created at the beginning of each sprint during the iteration planning meeting. This backlog consists of the tasks and user stories that the team commits to completing during the iteration. The process involves selecting the highest-priority items from the product backlog and breaking them down into smaller tasks that can be completed within the sprint timeframe.

A . Planning the Kanban board does not typically use an iteration backlog as Kanban is flow-based, not iteration-based.

B . At the beginning of each project is incorrect because the backlog is created for each sprint, not the entire project.

C . When defining the MBI (Minimum Business Increment) is related to identifying the smallest unit of value delivery but is not when an iteration backlog is created.