Question 1 - PMO-CP discussion
How many performance indicators should be used for each PMO function in each evaluation cycle?
A.
Only key functions should be monitored with performance Indicators, reducing bureaucracy and excessive control.
B.
One indicator per function, giving focus to what really matters.
C.
From two to four indicators, allowing the benefit of controlling to be compatible with the effort to achieve it.
D.
All the indicators recommended by the methodology.