The PMO Expectation Adherence indicator (pmo-EAl) is:

A.
The sum of 20% of the functions capable of generating 80% cumulative contribution probability.
Answers
A.
The sum of 20% of the functions capable of generating 80% cumulative contribution probability.
B.
The sum of the selected functions' contribution probabilities.
Answers
B.
The sum of the selected functions' contribution probabilities.
C.
The sum of the results of executed projects.
Answers
C.
The sum of the results of executed projects.
D.
The sum of 80% of the functions capable of generating 20% cumulative contribution probability.
Answers
D.
The sum of 80% of the functions capable of generating 20% cumulative contribution probability.
Suggested answer: B

Explanation:

The PMO Expectation Adherence Indicator (PMO-EAI) measures how well the PMO adheres to its expected contributions within an organization. The selected functions of the PMO are analyzed based on their contribution probabilities, which reflect how much they are expected to contribute to the overall project success.

The correct approach to calculating the PMO-EAI involves summing the probabilities of the contributions from these selected PMO functions. This method allows a clear assessment of the effectiveness of the PMO in meeting its objectives. It aligns with the principle of focusing on measurable outcomes in PMO performance evaluation, as seen in the application of frameworks like the PMBOK Guide and project evaluation models.