Question 19 - PMO-CP discussion
Essentially, to be successful and recognized, a PMO should be able to:
A.
Complete projects on agreed cost and time.
B.
Reduce the waste of resources on projects.
C.
Improve the business results of the organization.
D.
Generate perceived value for its stakeholders.
Your answer: