The evolution of PMO maturity occurs:

A.
When we Increase the amount of functions performed.
Answers
A.
When we Increase the amount of functions performed.
B.
When PMO functions become more sophisticated, whether operational, tactical or strategic.
Answers
B.
When PMO functions become more sophisticated, whether operational, tactical or strategic.
C.
When the PMO ceases to be operational and becomes increasingly strategic.
Answers
C.
When the PMO ceases to be operational and becomes increasingly strategic.
D.
When organizational maturity in project management evolves.
Answers
D.
When organizational maturity in project management evolves.
Suggested answer: B

Explanation:

The evolution of PMO maturity is not necessarily linked to the number of functions it performs, but rather to how sophisticated and aligned these functions are with the organization's strategic, tactical, and operational needs. A mature PMO moves beyond basic operational tasks, adopting strategic roles such as portfolio management and governance. This shift helps ensure that the PMO contributes effectively to achieving broader organizational goals, adding value through well-implemented processes.