Question 32 - PMO-CP discussion

Report
Export

Why is it necessary to understand who the PMO stakeholders are?

A.
Because It Is up to them to support the work of the PMO.
Answers
A.
Because It Is up to them to support the work of the PMO.
B.
Because they are the ones who pay the cost of the PMO.
Answers
B.
Because they are the ones who pay the cost of the PMO.
C.
Because their expectations of benefits should guide the PMO set up.
Answers
C.
Because their expectations of benefits should guide the PMO set up.
D.
Because they will be influenced by the work ot the PMO.
Answers
D.
Because they will be influenced by the work ot the PMO.
Suggested answer: C

Explanation:

Understanding who the PMO stakeholders are is critical because their expectations define the value and success metrics for the PMO. Stakeholders include executives, project sponsors, and others who have a vested interest in the outcomes of the PMO's work. Aligning the PMO's functions and objectives with these expectations ensures that the PMO is set up to deliver perceived value and meet the desired outcomes .