An administrator at Universal Containers has been asked to configure product schedules.

What should the administrator consider before enabling this feature?

A.
The Product Schedule is unavailable in Process Builder and Flow.
Answers
A.
The Product Schedule is unavailable in Process Builder and Flow.
B.
Line Item Schedule is unavailable In Process Builder and Workflow.
Answers
B.
Line Item Schedule is unavailable In Process Builder and Workflow.
C.
Customizable product schedule page layouts cannot be modified.
Answers
C.
Customizable product schedule page layouts cannot be modified.
D.
To remove o product schedule completely, remove It from the standard price book.
Answers
D.
To remove o product schedule completely, remove It from the standard price book.
Suggested answer: B

Explanation:

Product schedules allow users to track revenue or quantity over time for products in opportunities or orders by creating schedules manually or automatically based on predefined criteria such as start date, end date, frequency etc. However, product schedules have some limitations that administrators should consider before enabling this feature. One of these limitations is that line item schedules are unavailable in Process Builder and Workflow rules; only revenue schedules are available.

Reference: https://help.salesforce.com/s/articleView?id=sf.products_schedules_def.htm&type=5 https://help.salesforce.com/s/articleView?id=sf.products_schedules_considerations.htm&type=5