After completing requirements gathering session for a Sales Cloud implementation, the business analyst (BA) has started to write user stories. During an internal user story grooming session, the project manager decided that each user story must:
* Be assigned a level of effort
* Be demonstrated to the stakeholder
* Have documented deployment steps
Where should the DA capture these requirements?
A.
Definition of done
B.
Assumptions
C.
Acceptance criteria
Your answer: