The delivery team at Cloud Kicks is getting ready to demonstrate some new Sales Cloud functionality for a project's stakeholders. The business analyst has prepared a demo script, created test data in the sandbox, and tested the new functionality.

Which additional activity is most likely to result in a successful sprint demo?

A.
Conducting multiple dry runs
Answers
A.
Conducting multiple dry runs
B.
Exporting a backup copy of the demo data
Answers
B.
Exporting a backup copy of the demo data
C.
Performing a code review
Answers
C.
Performing a code review
Suggested answer: A

Explanation:

This answer states that conducting multiple dry runs is the additional activity that is most likely to result in a successful sprint demo for demonstrating some new Sales Cloud functionality for a project's stakeholders at Cloud Kicks. A dry run is a practice or a rehearsal of a presentation or a demonstration before the actual event. Conducting multiple dry runs means that the BA performs and repeats the presentation or the demonstration of the new Sales Cloud functionality several times before showing it to the project's stakeholders. Conducting multiple dry runs is the additional activity that is most likely to result in a successful sprint demo because it helps the BA to prepare and polish their presentation or demonstration skills, to identify and fix any errors or issues in the new Sales Cloud functionality, and to anticipate and address any questions or feedback from the project's stakeholders.

Reference: https://trailhead.salesforce.com/en/content/learn/modules/salesforce-business-analyst-quick-look/use-stakeholder-engagement-skills