If multiple teams are working on the same product, they should each have their own product backlog

False
False
True One product backlog per product
True One product backlog per product
Suggested answer: A
asked 23/09/2024
Jorrit Meijer
40 questions

Question 12

Report
Export
Collapse

When might a sprint be cancelled?

When the developers feel they aren't ready
When the developers feel they aren't ready
When the project manager decides this.
When the project manager decides this.
Never, the sprint must always be finished.
Never, the sprint must always be finished.
When the sprint goal becomes obsolete
When the sprint goal becomes obsolete
Suggested answer: D

Explanation:

The product owner can cancel the sprint if the sprint goal becomes obsolete. This is a very rare event. It can happen when a company losing a client or the client decides to take a completely different turn.

asked 23/09/2024
mohamed mamdouh
43 questions

Question 13

Report
Export
Collapse

The goal of the daily scrum is inspecting the progress toward the sprint goal and producing an actionable plan for the next day of work

False
False
True
True
Suggested answer: B

Explanation:

If you are not sure, review the daily scrum section in the scrum guide.

asked 23/09/2024
Sanjiv Cumar
38 questions

Question 14

Report
Export
Collapse

What is the commitment for the product backlog?

Product goal
Product goal
Sprint goal
Sprint goal
Sprint planning outcome
Sprint planning outcome
Definition of done
Definition of done
Suggested answer: A

Explanation:

If you are not sure, please review the section scrum artifacts in the scrum guide.

asked 23/09/2024
Spandana Gangavaram
32 questions

Question 15

Report
Export
Collapse

A scrum master is working with developers that are spread over different locations. They have a variety of meeting rooms and the daily scrum is a logistic struggle every day. What actions should the scrum master take?

Allow the developers to self-manage and decide what to do their selves.
Allow the developers to self-manage and decide what to do their selves.
Raise it as an impediment and make sure that management solves it.
Raise it as an impediment and make sure that management solves it.
Create a schedule and alternate who is responsible for the daily scrum logistics
Create a schedule and alternate who is responsible for the daily scrum logistics
Decide the best solution and arrange a meeting to inform the developers.
Decide the best solution and arrange a meeting to inform the developers.
Suggested answer: A

Explanation:

Self management is important. All the other options the scrum master takes a decision by himself, it is better if the solution comes from the development team.

asked 23/09/2024
Tim Wersinger
42 questions

Question 16

Report
Export
Collapse

Which are not true about scrum? Choose two.

Scrum is a framework for developing and sustaining complex products.
Scrum is a framework for developing and sustaining complex products.
Each component of scrum serves a specific purpose and is essential to Scrum's success
Each component of scrum serves a specific purpose and is essential to Scrum's success
Scrum is based on empirical process control
Scrum is based on empirical process control
Scrum is like traditional project management, but then with project managers replaced by self-management.
Scrum is like traditional project management, but then with project managers replaced by self-management.
Scrum is a methodology based on empirical process control.
Scrum is a methodology based on empirical process control.
Suggested answer: D

Explanation:

Scrum is not a methodology, because it doesn't fill in the details, it's a framework. Next to that, it is not like traditional project management where time, cost and scope are fixed.

asked 23/09/2024
Reinhard KOhl
38 questions

Question 17

Report
Export
Collapse

What is the purpose of a sprint retrospective? Choose two

Increase quality
Increase quality
Complain only in this session to avoid complaining in the rest of the sprint
Complain only in this session to avoid complaining in the rest of the sprint
Have more fun during the sprint
Have more fun during the sprint
Increase effectiveness
Increase effectiveness
Suggested answer: A

Explanation:

In the scrum guide it says: 'The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness.'

asked 23/09/2024
Yung-Shuen Chang
40 questions

Question 18

Report
Export
Collapse

The developers should have all the skills needed to:

Do all the work except for deployment
Do all the work except for deployment
Complete the work in the within the foreseen time and costs
Complete the work in the within the foreseen time and costs
Create a potentially releasable increment from the product backlog items
Create a potentially releasable increment from the product backlog items
Suggested answer: C

Explanation:

Developers are cross-functional, this means that they have all the skills necessary to create value each sprint.

asked 23/09/2024
Angela Cappa
34 questions

Question 19

Report
Export
Collapse

Which are topics of the sprint planning? Choose all that apply.

Why is this sprint valuable?
Why is this sprint valuable?
When is this sprint going to be done?
When is this sprint going to be done?
How to improve the scrum process in this sprint?
How to improve the scrum process in this sprint?
How will the selected work get done?
How will the selected work get done?
What can be done in this sprint?
What can be done in this sprint?
Who is going to do what?
Who is going to do what?
Suggested answer: A, D, E

Explanation:

These are the three topics mentioned in the scrum guide. Who is going to do what is not determined upfront, when the sprint will end is fixed and doesn't need to be discussed, what can be done to improve the process is for the sprint retrospective meeting.

asked 23/09/2024
mr Craig Ferguson
34 questions

Question 20

Report
Export
Collapse

During the sprint the developers realize that they have selected too many product backlog items. How should they go from there?

Inform the product owner and the stakeholders during the sprint review
Inform the product owner and the stakeholders during the sprint review
As soon as they realize they should work with the product owner to remove some work while not endangering the sprint goal
As soon as they realize they should work with the product owner to remove some work while not endangering the sprint goal
Outsource the work to another team
Outsource the work to another team
Use a definition of done with lower standards to be able to finish all the work they committed to
Use a definition of done with lower standards to be able to finish all the work they committed to
Suggested answer: B

Explanation:

Never should they reduce the DoD. They should be able to do the work their selves and therefore work with the product owner to reduce the scope. Since the product owner is responsible for maximizing value and making priorities, he is the go to person for matteres like this.