Question 20 - PSD discussion
During the sprint the developers realize that they have selected too many product backlog items. How should they go from there?
A.
Inform the product owner and the stakeholders during the sprint review
B.
As soon as they realize they should work with the product owner to remove some work while not endangering the sprint goal
C.
Outsource the work to another team
D.
Use a definition of done with lower standards to be able to finish all the work they committed to