During the sprint the developers realize that they have selected too many product backlog items. How should they go from there?

A.
Inform the product owner and the stakeholders during the sprint review
Answers
A.
Inform the product owner and the stakeholders during the sprint review
B.
As soon as they realize they should work with the product owner to remove some work while not endangering the sprint goal
Answers
B.
As soon as they realize they should work with the product owner to remove some work while not endangering the sprint goal
C.
Outsource the work to another team
Answers
C.
Outsource the work to another team
D.
Use a definition of done with lower standards to be able to finish all the work they committed to
Answers
D.
Use a definition of done with lower standards to be able to finish all the work they committed to
Suggested answer: B

Explanation:

Never should they reduce the DoD. They should be able to do the work their selves and therefore work with the product owner to reduce the scope. Since the product owner is responsible for maximizing value and making priorities, he is the go to person for matteres like this.