ExamGecko
Home / Scrum / PSD / List of questions
Ask Question

Scrum PSD Practice Test - Questions Answers, Page 3

List of questions

Question 21

Report
Export
Collapse

The three pillars of empirical process control are:

transparency
transparency
planning
planning
inspection
inspection
respect
respect
commitment
commitment
adaptation
adaptation
Suggested answer: A, C, F

Explanation:

If you are not sure, please review the Scrum theory section in the scrum guide

asked 23/09/2024
Kayode Omotosho
40 questions

Question 22

Report
Export
Collapse

Which statement best describes the sprint review?

It is a chance for inspecting the outcome of a sprint and determining the next steps
It is a chance for inspecting the outcome of a sprint and determining the next steps
It is a mechanism to control the work of the developers
It is a mechanism to control the work of the developers
It is a demo of the work that was done
It is a demo of the work that was done
Suggested answer: A, C

Explanation:

The scrum guide says: 'The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. '

asked 23/09/2024
B schatens
45 questions

Question 23

Report
Export
Collapse

What topics can be addressed during the sprint review? Choose the best answer.

The scrum process
The scrum process
All of these
All of these
The increment
The increment
Coding and engineering practices
Coding and engineering practices
Suggested answer: B

Explanation:

These are all potentional topics for the sprint review. If you are not sure, please read the sprint review section in the scrum guide again.

asked 23/09/2024
Jenny Silva
42 questions

Question 24

Report
Export
Collapse

What relation does scrum have to development practices?

Scrum requires a specific set of development practices
Scrum requires a specific set of development practices
Scrum is complemented by good development practices
Scrum is complemented by good development practices
Scrum requires all development practices
Scrum requires all development practices
Scrum has no relationship to development practices
Scrum has no relationship to development practices
Suggested answer: B

Explanation:

Scrum requires no development practices, but good development practices do help and make scrum more successful.

asked 23/09/2024
Andrew Staton
26 questions

Question 25

Report
Export
Collapse

Database design must be complete before coding starts to ensure a solid foundation

False
False
True
True
Suggested answer: A

Explanation:

The design grows as more is learnt.

asked 23/09/2024
Johnny Oostdijk
24 questions

Question 26

Report
Export
Collapse

What is a merge in a version control system?

Identifying a particular codebase as ready for distribution
Identifying a particular codebase as ready for distribution
Combining two or more versions of code into a single codebase
Combining two or more versions of code into a single codebase
Copying a portion of a codebase to isolate it from the original codebase
Copying a portion of a codebase to isolate it from the original codebase
Two or more developers working together to ensure proper coding and configuration management
Two or more developers working together to ensure proper coding and configuration management
Suggested answer: B

Explanation:

Merging means combining two different versions of the code into one version.

asked 23/09/2024
Dewald Van Schalkwyk
32 questions

Question 27

Report
Export
Collapse

In software development DRY refers to:

Code with low cyclomatic complexity
Code with low cyclomatic complexity
Code with minimal duplication
Code with minimal duplication
Code that has not been peer reviewed (yet)
Code that has not been peer reviewed (yet)
Code that has been peer reviewed
Code that has been peer reviewed
Suggested answer: B

Explanation:

DRY, don't repeat yourself

asked 23/09/2024
Veronica Puddu
54 questions

Question 28

Report
Export
Collapse

Who is responsible for a sprint backlog item that contains several database tasks?

The developers
The developers
Product owner
Product owner
The company's database specialist
The company's database specialist
Scrum master
Scrum master
Suggested answer: A

Explanation:

Developers are responsible for conducting the work on the sprint backlog

asked 23/09/2024
Nestor Quintero
40 questions

Question 29

Report
Export
Collapse

How is architecture decided in a scrum team during a project?

The developers emerge architecture as the system is created
The developers emerge architecture as the system is created
The architect works in the early part of each sprint to define the architecture of that sprint
The architect works in the early part of each sprint to define the architecture of that sprint
Upfront designs are presented to the developers prior to the first sprint
Upfront designs are presented to the developers prior to the first sprint
The architecture cares for itself as code is written and deployed
The architecture cares for itself as code is written and deployed
An architect on the team undertakes all architecture tasks
An architect on the team undertakes all architecture tasks
Suggested answer: A

Explanation:

Architecture emerges as more is created. There are often guidelines and principles in place.

asked 23/09/2024
MARTIN WEAVER
35 questions

Question 30

Report
Export
Collapse

What does a test written with TDD represent?

A technical requirement that must be satisfied
A technical requirement that must be satisfied
A bug
A bug
Great development practices
Great development practices
Something that completes the test coverage of a system
Something that completes the test coverage of a system
Suggested answer: A

Explanation:

The test gets written first in TDD, after that, the production code will be written to satisfy the test.

asked 23/09/2024
Richard Banks
44 questions
Total 120 questions
Go to page: of 12