Question 74 - PSD discussion
How much time will there be after a sprint before the next one starts?
A.
Enough to deploy the increment and update the product backlog based on the outcome of the sprint review
B.
Enough to clean up lingering definition of done points
C.
None, a new sprint starts immediately after the end of the previous one
D.
At most a week for a one-month sprint
Your answer: