Question 76 - PSD discussion

Report
Export

Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: A

Explanation:

The scrum guide says: 'The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint.'