Question 113 - CIS-ITSM discussion
A problem investigation had been previously closed, because the risk was accepted, in favor of using the workaround, instead of applying the fix. After a couple of weeks, the issue starts to occur more frequently, so management wants to re-visit the root cause analysis.
What would be the next step for this problem?
A.
If 7 days has passed, since the Problem was closed, it cannot be re-opened
B.
Problem Manager clicks Re-Analyze on the Problem record
C.
Problem Assignee clicks Re-Open on the Problem record
D.
Administrator clicks Re-Open on the Problem Record
Your answer: