Question 290 - Certified Business Analyst discussion
Sprint 1 of 5 has been completed in a Sales Cloud implementation. The business analyst (BA) met with the stakeholders to prioritize the backlog for the next sprint. One of the stakeholders wants to include a medium-priority item. There is still a list of high-priority items that need to be addressed.
How should the BA communicate with the stakeholder?
A.
Schedule a meeting to discuss the importance of the item, then re-evaluate all of the items and their priority levels
B.
Verify why the item is medium-priority, explain the reason, and determine if the item priority was misjudged compared to other items.
C.
Support the stakeholder in this decision, move the medium-priority item to the next sprint, and inform the development team.