What occurs when an individual enters a new commit date that is after the original planned date of a task?

A.
The assignee of any task that has the original task set as a predecessor is notified.
Answers
A.
The assignee of any task that has the original task set as a predecessor is notified.
B.
The Project Owner is notified whether this change will impact the Project Timeline.
Answers
B.
The Project Owner is notified whether this change will impact the Project Timeline.
C.
The Planned Completion Date of the task automatically changes to match the new Commit Date.
Answers
C.
The Planned Completion Date of the task automatically changes to match the new Commit Date.
Suggested answer: C

Explanation:

When a user updates the Commit Date to a date later than the original planned date in Adobe Workfront, the Planned Completion Date of the task is automatically updated to reflect the new commit date. This feature ensures that the timeline is adjusted based on the most current commitment by the task assignee, which can then impact downstream tasks and the overall project schedule.

This change streamlines project planning and helps keep task dependencies aligned with realistic completion expectations.