What occurs when an individual enters a new commit date that is after the original planned date of a task?
A.
The assignee of any task that has the original task set as a predecessor is notified.
B.
The Project Owner is notified whether this change will impact the Project Timeline.
C.
The Planned Completion Date of the task automatically changes to match the new Commit Date.